No trespassing, this site is under 24 hour video surveillance. 

Construction Update 10/2 – 10/13

Begin line striping in parking lots/road
Miscellaneous hydroseeding

Building 9

Construction: Continue caulking Ductile saw cuts
Complete installation of metal panels
Finish install of final dock leveler
Start painting punch list
Install lighting at metal panels (week of 10/9)

Building 12

Site work: Complete installation of signage
Hydroseed disturbed areas

Construction: Begin installation of bollards at dock doors
Begin metal panel installation (week of 10/9)
Begin painting bollards and guards (week of 10/9)
Begin caulking around doors frames and windows
Complete domestic water installation
Continue installing switchgear

PHASE 2 CONSTRUCTION PROGRESS

Binder is down on buildings 9 and 12